Energy Resources — Quick Revision

One-page CGPSC quick revision for Energy Resources: energy technologies, storage, hydrogen and nuclear facts in tables for last-minute Prelims and Mains.

6 min read Updated Oct 2026 #quick revision#cgpsc#energy resources

Conventional, renewable, storage, hydrogen and nuclear technology on one page. For explanations, go back to the chapter. For locations, states and plants, see Minerals and Energy Resources (Geography).

How to use this sheet
Scan it top to bottom in the week before Prelims. Bold entries are the facts examiners return to most often. Figures are dated; check current affairs for newer ones before Mains.

India’s Energy Numbers (as of July 2026 unless stated)

ItemFigure
Total installed capacity~552 GW
Non-fossil share~300.5 GW, over 54%; crossed 50% in June 2025
Solar / wind / hydro / bio~164.6 GW / ~58 GW / ~57 GW / ~11.8 GW
Nuclear24 reactors, 8,780 MW, 7 sites (NPCIL)
Pumped storage10 PSPs, ~7,425.6 MW operating (May 2026); Pinnapuram 1,680 MW largest
Crude import dependence~89% (2025-26)
2030 target500 GW non-fossil (COP26); net zero 2070
Nuclear target100 GW by 2047

Conventional Technology

FactDetail
1 unit1 kWh = 3.6 MJ
Capacity vs generationNon-fossil leads capacity; coal leads generation
Thermal plantRankine cycle: boiler → turbine → generator → condenser
Critical point of water~374 °C, 22.1 MPa
EfficiencySubcritical ~33–36%; supercritical ~38–40%; USC ~42%+
CG supercriticalSipat Stage-I 3 × 660 MW; Lara 2 × 800 MW
ESP / FGDFly ash / SO₂ → gypsum
Fly ash ruleMoEFCC, 31 Dec 2021: 100% utilisation; legacy ash by 2031
Coal gasificationSyngas = CO + H₂; 100 MT by 2030; ₹8,500 cr (Jan 2024); ₹37,500 cr (13 May 2026)
RefineryLightest at top: LPG, petrol, naphtha, kerosene, diesel, lubricants, fuel oil, wax, bitumen
Octane / cetanePetrol anti-knock / diesel ignition
BS-VI1 April 2020; 10 ppm sulphur
CNG / LNG / LPGCompressed methane / methane at −162 °C (~600× smaller) / propane + butane
OdorantEthyl mercaptan
Hydro power\( P = \rho g Q H \eta \)
TurbinesPelton high head · Francis medium · Kaplan low
Small hydroUp to 25 MW; large hydro counted as RE since March 2019

Renewable Technology

FactDetail
Solar PVPhotovoltaic effect, p–n junction, silicon; gives DC → inverter
Single-junction limit~33% (Shockley–Queisser)
Cell typesMono, poly, thin-film (CdTe, CIGS, a-Si), perovskite, bifacial
CSPMirrors → heat → steam turbine; heliostats; molten salt storage
Wind power\( P = \tfrac{1}{2}\rho A v^3 \); double speed → 8× power
Betz limit16/27 ≈ 59.3%
Offshore wind30 GW by 2030 target; VGF ₹7,453 cr for 1 GW (June 2024)
BiogasAnaerobic digestion; methane ~50–70% + CO₂
CBGPurified biogas (>90% methane); SATAT 2018; GOBARdhan 2018
Biofuel generations1G food · 2G residue (Panipat 2G ethanol) · 3G algae · 4G engineered
BiodieselTransesterification; Jatropha, used cooking oil
EthanolE20 reached 2025
GeothermalRadioactive decay; binary cycle; Tattapani (Balrampur, CG); policy 15 Sep 2025; no commercial plant
Tidal / OTECHigh tidal range (Khambhat) / ~20 °C difference (Kavaratti LTTD)

Storage and Hydrogen

FactDetail
Duck curveMidday dip, steep evening ramp
Pumped storagePump up when cheap, generate at peak; ~70–80% round trip
Li-ionGraphite anode; NMC (EVs) or LFP (grid; no cobalt or nickel)
Sodium-ion / flowAbundant sodium / liquid electrolytes in tanks (vanadium redox)
PLI ACCMay 2021; ₹18,100 cr; 50 GWh
BESS VGF2023 scheme; ₹5,400 cr for 30 GWh (June 2025)
Battery Waste Management Rules2022; EPR
Fuel cellH₂ + O₂ → electricity + water; no combustion; PEM for vehicles
ElectrolyserReverse of fuel cell: alkaline, PEM, solid oxide
Hydrogen coloursGrey (gas, SMR) · Blue (gas + CCS) · Brown (coal) · Turquoise (pyrolysis) · Pink (nuclear) · Green (RE electrolysis)
Green Hydrogen Mission4 Jan 2023; ₹19,744 cr; 5 MMT/yr by 2030; ~125 GW RE; SIGHT
Green hydrogen standard≤ 2 kg CO₂e per kg H₂ (Aug 2023); BEE accredits
Hydrogen hubsDeendayal (Kandla), V.O. Chidambaranar (Tuticorin), Paradip (Sept 2025)
CG linkKatghora: first lithium block auctioned (June 2024)

Nuclear

FactDetail
Natural uranium~99.3% U-238, ~0.7% U-235
Fission~200 MeV per U-235 fission; 2–3 neutrons; chain reaction; criticality k = 1
FusionD + T → He + n + 17.6 MeV; tokamak; ITER at Cadarache, France; India member since 2005
Fissile / fertileU-235, Pu-239, U-233 / U-238, Th-232
ModeratorSlows neutrons: heavy water, light water, graphite
Control rodsAbsorb neutrons: boron, cadmium, hafnium
PHWRNatural U + heavy water; India’s workhorse; 700 MW units (Kakrapar first)
BWR / VVERTarapur (1969, first) / Kudankulam (largest)
FBRNo moderator; liquid sodium coolant; MOX fuel
Fuel cycleJaduguda, Tummalapalle (UCIL) → NFC Hyderabad → reactor → reprocessing (Trombay, Tarapur, Kalpakkam) → vitrification
India’s cycleClosed (reprocessing)
Three stagesPHWR (nat. U → Pu) → FBR (Pu, breeds Pu and U-233) → thorium + U-233
FBTR / PFBR / KAMINI1985 / 500 MWe, BHAVINI, criticality 6 April 2026 / U-233 fuelled, 30 kW
ThoriumMonazite sands (Kerala, Odisha, AP, TN); ~11.93 MT monazite (AMD)
InstitutionsAEC 1948; DAE 1954; BARC (name from 1967); AERB 1983; NPCIL 1987
Nuclear Energy MissionBudget 2025-26; ₹20,000 cr SMR R&D; 5 SMRs by 2033; 100 GW by 2047
SMRsBSR (220 MW PHWR, captive for steel and aluminium); BSMR-200; SMR-55
SHANTI Act 2025Assent 20 Dec 2025; replaces AEA 1962 + CLNDA 2010; private entry; statutory AERB; operator liability
AccidentsThree Mile Island 1979; Chernobyl 1986 (RBMK); Fukushima 2011

Don’t Confuse

ThisvsThat
CNG, LNG: methanevsLPG: propane + butane
Octane: petrolvsCetane: diesel
ESP: fly ashvsFGD: SO₂
Solar PV: light → DCvsCSP: light → heat → turbine
Biogas: CH₄ + CO₂ (anaerobic)vsProducer gas / syngas: CO + H₂
Tidal: tidal rangevsOTEC: temperature difference
Fuel cell: makes electricityvsElectrolyser: makes hydrogen
Green H₂: RE electrolysisvsBlue H₂: gas + carbon capture
Moderator: slows neutronsvsControl rods: absorb neutrons
Fissile (U-235, Pu-239, U-233)vsFertile (U-238, Th-232)
PHWR: natural UvsPWR/BWR: enriched U
Tarapur: firstvsKudankulam: largest
Capacity sharevsGeneration share
Favourite MCQ trap
“Thorium can be used directly as reactor fuel.” Wrong. Thorium-232 is fertile: it must absorb a neutron and decay to U-233 before it can sustain fission. That conversion is why India needs stage 2 fast breeders before stage 3.
Second favourite trap
“Over half of India’s electricity now comes from non-fossil sources.” Wrong. Over half of installed capacity is non-fossil (July 2026), but coal still generates most of the electricity, because solar and wind have low capacity factors.